Managing Projects with Microsoft Project 2013

Here you have the best Microsoft 74-343 practice exam questions

  • You have 101 total questions to study from
  • Each page has 5 questions, making a total of 21 pages
  • You can navigate through the pages using the buttons at the bottom
  • This questions were last updated on December 12, 2025
  • This site is not affiliated with or endorsed by Microsoft.
Question 1 of 101
Your organization uses Project Professional 2013 and records actual hours worked on the project.
You manage a small e-commerce website implementation project. One of your testers asks for assistance in completing a critical task, and you find two additional testing resources that can assist with executing the critical test cases.
The total estimated work for the effort-driven task is 100 hours. The original testing resource, Resource1, completes 25 hours of work on the task.
You need to add Resource2 and Resource3 to the task and split the remaining hours across all three resources now working on the task.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Correct Answer: A, C

Question 2 of 101
You are managing a project using Project Professional 2013.
Your project schedule is showing task overallocation indicators in the Gantt chart view. You navigate to the Team Planner view to investigate more details regarding the over allocations.
You discover that the BA1 resource is overallocated and you need to see all assignments with details for BA1 to understand their current workload before making any assignment changes.
What should you do?
Correct Answer: B

Question 3 of 101
You are a project manager who uses Project Standard 2013.
You are creating a preliminary project schedule and are estimating the number of resources required prior to finalizing the schedule. You do not have named resources to complete the tasks, but you know the resource roles that are necessary. One of the roles needed is architect.
You need to estimate how many architect hours are required to complete the work.
What should you do?
Correct Answer: C

Question 4 of 101
Your company uses Project Professional 2013.
You are setting up a preliminary schedule by using manually scheduled tasks. You create a task with no duration, start, or finish date, and then you assign a resource. Later, you enter a duration of three days for that task.
You need to let the resource know how the Work will be affected.
What should you say?
Correct Answer: A

Question 5 of 101
You are a program manager who uses Project Professional 2013.
You manage a portfolio of projects for a large point of sale implementation. All of your project managers have created individual project schedules. You discover that you have resource constraints since multiple resources are working on multiple projects.
You need visibility into resources across all projects so that you can most efficiently manage the resources and their availability.
What should you do?
Correct Answer: A