Question 1 of 53

Whose interests are specifically represented by the senior supplier?

1. Those ensuring the project is value for money.

2. Those who will use the project's products.

3. Those who will be developing the project's products.

4. Those responsible for the project's technical integrity.

    Correct Answer: C

    The senior supplier specifically represents the interests of those who will be developing the project's products and those responsible for the project's technical integrity. The senior supplier's role is to ensure the quality and technical correctness of the products being developed. They oversee and facilitate the production process and are responsible for maintaining the project's technical specifications and standards.

Question 2 of 53

Which is a key objective of running a workshop?

    Correct Answer: B

    A key objective of running a workshop is to encourage collaboration and create the defined outputs from the event. Workshops are designed to bring together participants to work collectively towards shared goals, leveraging their diverse knowledge and skills to achieve specific outcomes.

Question 3 of 53

Which statement about the waterfall methodology definition is CORRECT?

    Correct Answer: B

Question 4 of 53

How should product-based planning be used as part of PRINCE2 Agile?

    Correct Answer: D

Question 5 of 53

Which statement about the 'directing a project' process is CORRECT?

    Correct Answer: A

    The project board's primary role in the 'directing a project' process is to provide overall direction and management for the project. One of their responsibilities is to attend regular project progress meetings. These meetings allow the project board to monitor the project's progress, review the project plan, make key decisions, and ensure that the project aligns with the business case. Attending these meetings helps the project board stay informed and address any issues or risks that arise during the project's lifecycle.