Question 1 of 374

Which of the following statements describes an outcome?
Answer

Suggested Answer

The suggested answer is C.

An outcome is a measurable improvement that results from a change. It reflects the positive impacts that a project aims to achieve. Therefore, the correct option is 'A measurable improvement resulting from a change.'

Community Votes

No votes yet

Join the discussion to cast yours

Question 2 of 374

Which of the following should NOT be included in the business case?
Answer

Suggested Answer

The suggested answer is D.

The business case typically includes reasons, major risks, and business options, as these elements are essential for decision-making and understanding the context and potential challenges of the project. The business approach, however, usually refers to the specific strategy or methodology for how the business will operate or implement its plans, which is not typically part of the business case document.

Community Votes

No votes yet

Join the discussion to cast yours

Question 3 of 374

When considering the business options in the business case, which of these is NOT an option?
Answer

Suggested Answer

The suggested answer is D.

In a business case, typical options considered include 'Do nothing', which represents the baseline scenario, 'Do the minimum', which entails implementing the least effort necessary, and 'Do the maximum', which involves implementing the most extensive option. 'Do something' is not a specific or standard option in a business case as it lacks definition and specificity compared to the other clearly defined options.

Community Votes

No votes yet

Join the discussion to cast yours

Question 4 of 374

Which of the following statements is TRUE with regard to expected benefits?
Answer

Suggested Answer

The suggested answer is C.

Expected benefits should be measurable to ensure they can be tracked and evaluated effectively. This allows for clear assessment of whether the benefits have been achieved. Measurements provide a concrete basis for analysis and reporting in alignment with project or corporate objectives.

Community Votes

No votes yet

Join the discussion to cast yours

Question 5 of 374

Who is responsible for ensuring that the value-for-money solution is constantly reassessed?
Answer

Suggested Answer

The suggested answer is A.

Business Assurance is responsible for ensuring that the value-for-money solution is constantly reassessed. In project management, particularly within frameworks like PRINCE2, Business Assurance encompasses the responsibilities of overseeing the business case and benefits realization. This role includes continuously evaluating whether the project remains a viable and cost-effective investment for the business.

Community Votes

No votes yet

Join the discussion to cast yours

About the PRINCE2 PRINCE2-Practitioner Edition 6 Certification Exam

About the Exam

The PRINCE2 PRINCE2-Practitioner Edition 6 (PRINCE2 Practitioner Edition 6) validates your knowledge and skills. Passing demonstrates proficiency and can boost your career prospects in the field.

How to Prepare

Work through all 374 practice questions across 75 pages. Focus on understanding the reasoning behind each answer rather than memorizing responses to be ready for any variation on the real exam.

Why Practice Exams?

Practice exams help you familiarize yourself with the question format, manage your time, and reduce anxiety on the test day. Our PRINCE2-Practitioner Edition 6 questions are regularly updated to reflect the latest exam objectives.