Question 1 of 45
For a specific Sprint Backlog item that has been started, what is the best chart (analytic) to determine when it will be finished?
Correct Answer: A

Question 2 of 45
What might a Scrum Team visualize with Kanban? (Choose three.)
Correct Answer: A, B, C

Question 3 of 45
Which of the following is NOT a flow metric?
Correct Answer: E

Question 4 of 45
As input for Daily Scrum, which metrics are likely to provide the most actionable data?
Correct Answer: A

Question 5 of 45
Within the same Kanban system, Work in Progress (WIP), is NOT a leading indicator for:
Correct Answer: D