Question 1 of 144
When considering risks, which describes an opportunity in a project?
Correct Answer: B

Question 2 of 144
Which of the following statements about lines of authority and reporting are true?
1, The Project Manager has day-to-day control for a management stage within the limits laid,
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
Correct Answer: C

Question 3 of 144
Which may be funded from a risk budget?
Correct Answer: C

Question 4 of 144
What is the first task of product-based planning?
Correct Answer: B

Question 5 of 144
How many tasks does the product-based planning technique describe?
Correct Answer: D