Which of the following activities is the Executive responsible for?
DRAG DROP -
BUSINESS CASE -
Here are three statements from the business case for the Health and Safety Project.
Under which heading in the business case (A-F) should they be recorded?
Choose only one heading for each statement. Each heading can be used once, more than once, or not at all.
Select and Place:

The executive has asked the project manager to plan for the 'e-learning course' to be used as soon as it is accredited. The aim is to start selling the 'e-learning course' while the remainder of the outputs relating to classroom-based delivery are finished. The sales of the 'e-learning course' will be entered into the business case.
Why is the executive's decision to deliver the benefits early appropriate for managing the business case?
During stage 3, the project scope was extended to include a practice test for learners to take during the training course. The cost of this test will be included in the cost of the course.
The change to project scope was approved and the cost of ֲ£2,500 was paid for from the change budget. The project manager documented an increase of ֲ£2,500 in the project budget in the business case.
Is this an appropriate action, and why?
When updating the project plan as part of Managing a stage boundary, what else might be updated?