GIAC Certified Project Manager

Here you have the best GIAC GCPM practice exam questions

  • You have 355 total questions to study from
  • Each page has 5 questions, making a total of 71 pages
  • You can navigate through the pages using the buttons at the bottom
  • This questions were last updated on January 17, 2026
  • This site is not affiliated with or endorsed by GIAC.
Question 1 of 355
FILL BLANK -
______________ emphasizes on bringing out the best in a team to make sure that self-development, positive communication, leadership skills, and the skill to work together as a team to resolve problems are built within the team.
Correct Answer:

Question 2 of 355
Which of the following is a formal documentation that indicates the completion of the project or phase and the transfer of the completed project deliverables to the operations group or to the next phase?
Correct Answer: C
As part of the project closure activities, the project handover report is a formal documentation that indicates the completion of the project or phase and the transfer of the completed project deliverables to the operations group or to the next phase.
Answer option D is incorrect. A project charter is a document that officially recognizes and acknowledges that a project exists. It helps define requirements and expectations to all involved in the project. It is issued by the project sponsor. It can be as simple as a one-page form for a very small project, briefly describing the project and listing the responsibilities and authority of the project manager. Charters can be much longer, however, depending on the size of the project. In addition to formally authorizing a project, the charter provides the project manager with the authority to apply organizational resources to project activities. Project charters are important to the success of a project.
It's a good idea to have a project manager assigned to the project prior to the start of planning, and preferably while the project charter is being developed. Here's an example of a project charter.
Exam GCPM: Question 2 - Image 1
Answer option B is incorrect. A risk register is a document that contains the results of qualitative risk analysis, quantitative risk analysis, and risk response planning. Description, category, cause, probability of occurring, impact on objectives, proposed responses, owner, and the current status of all identified risks are put in the risk register.
Answer option A is incorrect. The stakeholder register is a project management document that contains a list of the stakeholders associated with the project. It assesses how they are involved in the project and identifies what role they play in the organization. The information in this document can be very perceptive and is meant for limited exchange only. It also contains relevant information about the stakeholders, such as their requirements, expectations, and influence on the project.
Reference: "Project Management Body of Knowledge (PMBOK Guide), Fourth edition"
Chapter: Procurement and Project Integration
Objective: Monitoring Your Projects Progress C
Question 3 of 355
Which of the following processes is described in the statement below?
"It is involved with many kinds of process design and with implementation and improvement to the IT infrastructure and service processes."
Correct Answer: B

Question 4 of 355
FILL BLANK -
Fill in the blank with the appropriate term.
The ________________ defines the period in which, during the development of the project scope statement, a clear and very thorough project scope statement narrative is documented.
Correct Answer:

Question 5 of 355
Which of the following staffing management plan factors is described in the statement below?
"It helps promote and reinforce desired behaviors of team members."
Correct Answer: A