GIAC Certified Project Manager

Here you have the best GIAC GCPM practice exam questions

  • You have 346 total questions to study from
  • Each page has 5 questions, making a total of 70 pages
  • You can navigate through the pages using the buttons at the bottom
  • This questions were last updated on October 17, 2025
  • This site is not affiliated with or endorsed by GIAC.
Question 1 of 346
FILL BLANK -
______________ emphasizes on bringing out the best in a team to make sure that self-development, positive communication, leadership skills, and the skill to work together as a team to resolve problems are built within the team.
    Correct Answer:

Question 2 of 346
FILL BLANK -
Fill in the blank with the appropriate term.
______________________ involves the implementation of strategies to reduce the negative aspects of conflict and to increase the positive aspects of conflict at a level equal to or higher than where the conflict is taking place.
    Correct Answer:

Question 3 of 346
Lamont is the project manager of a project that has recently finished the final project deliverables. The project customer has signed off on the project deliverable and Lamont has a few administrative closure activities to complete. In the project, there were several large risks that could have wrecked the project but Lamont and his project team found some creative methods to resolve the risks without affecting the project costs or project end date. What should Lamont do with the risk responses he identified during the project's monitoring and controlling process?
    Correct Answer: B

Question 4 of 346
You are the project manager for your organization. Marcy, a project stakeholder, is demanding that you add some deliverables to your project scope for free. You explain to Marcy that it's too late in the project execution to consider adding these deliverables, as most of the software your project team is creating is nearly done. Marcy and you escalate the issue to management. Management decides that you will add the deliverables to the project scope if Marcy pays a significant fee and allows you additional time to complete the project. What conflict resolution method has management offered?
    Correct Answer: B

Question 5 of 346
You are project manager of HHK project. Examine the network diagram given below:
Exam GCPM: Question 5 - Image 1
A vendor reports that he will be four days late on the materials you'll need in order to complete Activity E. Based on the project network diagram, how many days can Activity E be delayed?
    Correct Answer: C