The executive has confirmed that ABC Company's annual business plan includes the benefits that the Health and Safety Training Project is expected to deliver.
The executive has therefore advised the project manager that this provides sufficient business justification for the project during the 'starting up a project' process.
As a result, the project manager will not need to produce an outline business case.
Is this an appropriate application of the 'business case' theme, and why?