Question 6 of 80

Which of the following parameters are available when you define a new maintenance plan category? (Choose three.)

Answer

Suggested Answer

The suggested answer is A, B, C.

Question 7 of 80

You want to create a single-cycle plan with a cycle of 12 months. You use the scheduling indicator Time - key date.

The orders should be called 3 months before the planned date.

How can you set up the maintenance plan? (Choose two.)

Answer

Suggested Answer

The suggested answer is C.

Community Votes7 votes
CSuggested
86%
A
14%
Question 8 of 80

You want to set up a general maintenance task list for inspection rounds using the overall time confirmation as a simplified way to record measurement documents. What do you need to do? (Choose two.)

Answer

Suggested Answer

The suggested answer is A, B.

Question 9 of 80

You create two maintenance packages and only one package should be executed at a time. Which parameter determines this?

Answer

Suggested Answer

The suggested answer is B.

Community Votes4 votes
BSuggested
100%
Question 10 of 80

You want to set up a scenario for regular maintenance. The first event should take place after 1 year; after that, it is a regular cycle of 6 months.

Which parameter do you have to use to map this in the system?

Answer

Suggested Answer

The suggested answer is A.