Question 6 of 75
A FlashArray//XR2/3 has an Ethernet mezzanine (EMEZZ), what are the interface names of the ports on the mezzanine?
Correct Answer: A

Question 7 of 75
What should an Implementation Engineer do when installing rails in a threaded-hole rack?
Correct Answer: A

Question 8 of 75
Support requests a powercycle on a newly-installed FlashArray. What is the correct way to perform this action?
Correct Answer: C

Question 9 of 75
Before leaving the site after an install, who is required to provide completion sign-off?
Correct Answer: B

Question 10 of 75
Prior to running the puresetup newarray command, which command should an Installation Engineer run on a new install of an //XR4 array?
Correct Answer: B