Project+

Here you have the best CompTIA PK0-004 practice exam questions

  • You have 588 total questions to study from
  • Each page has 5 questions, making a total of 118 pages
  • You can navigate through the pages using the buttons at the bottom
  • This questions were last updated on December 20, 2024
Question 1 of 588

A project manager is attempting to establish the proper sequencing and duration of project activities.

Which of the following would be the MOST beneficial?

    Correct Answer: A

    To establish the proper sequencing and duration of project activities, a network diagram is the most beneficial tool. A network diagram visually depicts the project activities and their dependencies or relationships. It shows the sequence in which tasks should be performed and can help in identifying the critical path, which is essential for understanding the project's timeline. While a Gantt chart is useful for displaying schedules and durations graphically, it is typically used after the project activities have already been sequenced and their durations determined. Therefore, for establishing sequencing and duration, the network diagram is more advantageous.

Question 2 of 588

Which of the following are characteristics of a project? (Choose two.)

    Correct Answer: B, C

    The two main characteristics of a project are that it is temporary and that it has a start and finish. A project is temporary because it has a defined beginning and end in time, which indicates a specific duration. It also involves a series of tasks that are completed to achieve specific objectives, thus having distinct initiation and completion points. These traits distinguish projects from ongoing operations, which are continuous and lack a definite end date.

Question 3 of 588

A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services.

Which of the following documents will the company MOST likely release FIRST?

    Correct Answer: B

    The correct document to release first when a company determines it lacks the in-house capability to perform a project and seeks third-party services is a Request for Information (RFI). RFIs are used to gather general information about the capabilities of various vendors and options available in the market. It helps the company understand who can provide the required services and at what potential cost, allowing for a more informed decision in subsequent procurement steps.

Question 4 of 588

The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation.

Which of the following should the project manager bring to the meeting to support this recommendation? (Choose two.)

    Correct Answer: A, D

    To support the recommendation for the removal of a vendor, the project manager should bring the issue log and the procurement plan. The issue log will provide specific reasons and documented instances of why the vendor should be replaced, illustrating the problems and challenges faced with the current vendor. The procurement plan is important to outline the process and considerations for selecting, managing, and replacing vendors. This plan provides a structured approach to procurement which would help justify the next steps in selecting a new vendor.

Question 5 of 588

A project manager is creating the WBS.

In which of the following phases is the project?

    Correct Answer: B

    The project is in the Planning phase when the project manager is creating the Work Breakdown Structure (WBS). The Planning phase involves defining all aspects of the project including scope, deliverables, and scheduling, and the WBS is a critical tool for organizing and defining the total scope of the project. In the Initiation phase, the project is just starting and the focus is on defining the scope and objectives. The Execution phase involves carrying out the work according to the project plan, and the Closing phase involves finalizing all aspects and closing out the project.