PRINCE2 Agile Foundation Exam - Question 29


How is the 'tailor to suit the project' principle applied in an agile context?

Show Answer
Correct Answer: C

In an agile context, the 'tailor to suit the project' principle is best applied by using the Agilometer to assess the project environment. The Agilometer helps in evaluating the project's need for agility, which guides how the agile approach should be tailored to fit the specific characteristics and risks of the project environment. It directly addresses tailoring by considering factors such as customer engagement and communication ease, ensuring the agile methodology is appropriately adjusted for the project.

Discussion

6 comments
Sign in to comment
AJ2021
Dec 23, 2022

Correct Answer: C. By using the Agilometer to assess the project environment. Page 40 of official book v2018

alice07
Jan 8, 2024

The correct answer is C as agreed with the comment below. A is "Focus on the Product" - by flexing what is delivered to make it easy to stay in control.

DjtomipOption: C
Oct 5, 2024

In that case, for the application of the "tailor to suit the project" principle in the context of PRINCE2 Agile, the more precise choice is: C. By using the Agilometer to assess the project environment. This option directly references a tool within PRINCE2 Agile that helps evaluate the project's need for agility and guides the tailoring of the approach accordingly.

KayBatahOption: C
Oct 26, 2024

7.3 Guidance on applying the PRINCE2 principles Table 7.1 Overview of the guidance when applying PRINCE2 principles in an agile context Tailor to suit the project environment PRINCE2 Agile incorporates an agile assessment tool (the Agilometer: see Chapter 24), which enables further specific tailoring by assessing the risks associated with the agile way of working with respect to the project environment (e.g. How engaged is the customer? How easy is communication?).

user0044
Mar 1, 2024

for quality Prince2 training in Pakistan, visit this trainer’s website: https://www.javedpmp.com/prince2-certification-training.php

Djtomip
Sep 22, 2024

A. By flexing what is produced to stay in control and deliver value. In an Agile context, the "tailor to suit the project" principle is applied by flexing what is produced to stay in control and deliver value. This means that the Agile approach is tailored to the specific needs of the project, rather than trying to force a one-size-fits-all approach. The Agile Manifesto emphasizes the importance of responding to change and delivering working software frequently, which requires a flexible and adaptable approach. This means that the Agile team must be able to adjust their approach to suit the specific needs of the project and respond to changing requirements and priorities. By tailoring the Agile approach to the project, the team can stay in control of the project and ensure that they are delivering value to the customer. This may involve adjusting the Agile ceremonies, such as Sprint Planning or Daily Scrum, to better suit the needs of the project, or incorporating additional practices or tools to address specific project requirements.