This information was gathered during the Assessment Phase:
✑ There is a performance based SLA for East "" West traffic.
✑ The business critical applications require prioritization of their traffic.
✑ One of the services is a file share and has a high demand for bandwidth.
Which selection should the architect include in their design? (Choose the best answer.)
This information was gathered during the Assessment Phase:
✑ Customer currently has a single 10 host vSphere cluster.
✑ Customer wants to improve network security and automation.
✑ Current cluster utilization and business policies prevent changing the existing vSphere deployment.
✑ High-availability is important to the customer.
Which three selections should the architect include in their design? (Choose three.)
This information was gathered by the architect during the Discover Task of the Enagagement Lifecycle:
✑ There are applications which use IPv6 addressing.
✑ Network administrators are not familiar with NSX-T Data Center solutions.
✑ Hosts can only be configured with two physical NICs.
✑ There is an existing management cluster to deploy the NSX-T components.
✑ Dynamic routing should be configured between the physical and virtual network.
✑ There is a storage array available to deploy NSX-T components.
Which constraint was documented by the architect? (Choose the best answer.)