The suggested answer is D.
In this scenario, the customs procedures are complex and frequently changing, and the project team has identified that equipment delays are likely. The word 'likely' indicates a high probability of the risk occurring. Additionally, given that these equipment delays could lead to the cancellation of the project, the impact is also high. Therefore, the risk should be characterized as having high probability and high impact.