Who should update the work estimates during the Sprint?
A.
Only the team members
B.
The Project Manager
C.
The Product Owner
Answer
Discussion
Correct Answer: A
Question 7 of 59
Which means of communication is the most preferable to clarify the interpretation of a requirement?
A.
E-mail
B.
Face-to-face
C.
Instant messaging
D.
Telephone
Answer
Discussion
Correct Answer: B
Question 8 of 59
In a Scrum project, when would a requirement get added to the Product backlog?
A.
When it is developed, but cannot yet be released.
B.
When the team works on it for a particular release.
C.
When the customer requests a new requirement.
Answer
Discussion
Correct Answer: C
Question 9 of 59
Under what circumstances would a team use Affinity Estimation Technique instead of Planning Poker?
A.
If more details are needed during Sprint Planning
B.
If there is a large number of stories to estimate
C.
If there is a small number of stories to estimate
Answer
Discussion
Correct Answer: B
Question 10 of 59
What is the objective of the Scrum-of-Scrums meeting?
A.
To inform management about the progress of the project.
B.
Bring together all team members of all teams.
C.
Coordinate the work of multiple Scrum teams.
D.
Kick-off an international Scrum project.
Answer
Discussion
Correct Answer: C