Question 6 of 59
What is the primary responsibility of a Scrum Master in order to keep a Scrum team working at its peak level of productivity?
Correct Answer: C

Question 7 of 59
A customer requests a report that summarizes functionality added and defects found and fixed, right at the end of a Sprint.
Who may best prepare this report?
Correct Answer: B

Question 8 of 59
Who should update the work estimates during the Sprint?
Correct Answer: A

Question 9 of 59
Which means of communication is the most preferable to clarify the interpretation of a requirement?
Correct Answer: B

Question 10 of 59
In a Scrum project, when would a requirement get added to the Product backlog?
Correct Answer: C