The suggested answer is C.
Once the project manager has defined the tasks, durations, resources, and costs, the next logical step is to seek baseline approval. This step involves getting formal acceptance from the project stakeholders on the defined scope, schedule, and budget, which ensures that everyone has a mutual understanding and agreement on the project plan. Approval of the baseline is crucial as it will serve as the standard for measuring project performance throughout its lifecycle.