When is a change task for Post Implementation Review created for an unauthorized change?
When is a change task for Post Implementation Review created for an unauthorized change?
A change task for Post Implementation Review is created when the change request moves to a state of Review. This step ensures that unauthorized changes undergo a thorough review before any further actions are taken and aligns with standard ITSM practices.
The correct answer is C When an unauthorized, Emergency Change Request record moves to a state of Review, a change task for Post Implementation Review is automatically created. ITSM Implementation book page(454)
Page 446 now.
It is C. Tested in Tokyo PDI. Created an unauthorized change, went straight to the "Review" state with a Post Implementation Review change task created.
correct
Tokyo eBook p454
correct
correct answer is C
textbook p289
correct
Correct answer is C
Agreed, answer is C
answer is C
The correct answer is C.
When an unauthorized Emergency Change Request record moves to a state of Review, a change task for Post Implementation Review is automatically created.
A - this is a post implementation meaning after it was done.
Correct answer is C
Page 446 ITSM Implementation book: When an unauthorized, Emergency Change Request record moves to a state of Review, a change task for Post Implementation Review is automatically created.
448- itsm implementation book tokyo