CIS-RC Exam QuestionsBrowse all questions from this exam

CIS-RC Exam - Question 4


Which of the following statements is true of a Risk Response task?

Show Answer
Correct Answer: D

The Risk Response task is automatically progressed through the states using a workflow. This means that the task’s states are managed by a predefined workflow, ensuring a structured and consistent process.

Discussion

6 comments
Sign in to comment
esllinOption: A
Jul 5, 2023

Only one response task is opened at a time. Textbook P257

stophsOption: D
Nov 20, 2023

d is correct

stophsOption: D
Dec 1, 2023

d is correct

ss2780
Apr 26, 2024

A is the correct answer. The link to the product page does not mention that risk admin role is required. The textbook clearly states that risk manager is required to assign the risk response task. Page - 258 of the text book.

Livut
Sep 1, 2024

I really don't understand this question. You can add multiple risk response tasks to a risk, I just did that and there is no workflow that controls the states of a risk response task

PurushothamanDOption: D
Feb 24, 2025

D is correct: Eliminating other responses: A: A risk can have multiple risk responses. Its the fundamental of risk management. B: An assessor then creates risk response tasks and assigns them to the risk user with the role sn_risk.user. C: Based on documentation, risk manager role is sufficient to assign risk response task D: This risk response has a workflow except for an object assessment.