CQE Exam - Question 2


Which of the following is NOT considered a prevention cost?

Show Answer
Correct Answer: CD

Prevention costs are incurred to prevent defects and ensure high quality in the production process. These usually include activities such as writing operating procedures, training personnel, and maintaining equipment to ensure it runs correctly. Data acquisition and analysis, however, falls more squarely under appraisal costs, as it involves evaluating and quantifying the quality and performance of the product. Therefore, data acquisition and analysis is not considered a prevention cost.

Discussion

1 comment
Sign in to comment
Sachindra_89Option: D
Jan 14, 2023

Calibration & testing procedure is not consider as prevention.