You are a project manager in an organization that uses Microsoft PPM. You create a proposal for a new project by entering values for the Name, Description,
Proposed Cost, Proposed Benefits, and Sponsor Name properties.
The PMO must be able to approve all project proposals that have a proposed cost above a certain threshold value.
You need to use a project approval workflow.
Which three objects should use? Each correct answer presents part of the solution.