Managing Projects and Portfolios with Microsoft PPM

Here you have the best Microsoft 70-348 practice exam questions

  • You have 48 total questions to study from
  • Each page has 5 questions, making a total of 10 pages
  • You can navigate through the pages using the buttons at the bottom
  • This questions were last updated on December 11, 2025
  • This site is not affiliated with or endorsed by Microsoft.
Question 1 of 48
You are a project manager in an organization that uses Microsoft PPM. You create a proposal for a new project by entering values for the Name, Description,
Proposed Cost, Proposed Benefits, and Sponsor Name properties.
The PMO must be able to approve all project proposals that have a proposed cost above a certain threshold value.
You need to use a project approval workflow.
Which three objects should use? Each correct answer presents part of the solution.
Correct Answer: B, C, E

Question 2 of 48
You use Microsoft PPM to manage an e-commerce portal development program.
The program is separated into individual projects that represent each area of development. This allows each group to manage its own tasks while still having progress visibility at the program level.
You need to be able to see all programs and their associated individual projects from within Project Center.
What should you do?
Correct Answer: C

Question 3 of 48
You are the Microsoft PPM administrator for a large company. The IT manager uses four business drivers for prioritization. The priority of all four drivers is set at
25 percent.
The IT manager adds an additional business driver that has a priority value set to 30 percent.
You need to create a new prioritization that includes the additional business driver.
What should you do?
Correct Answer: C

Question 4 of 48
You are using Microsoft PPM to manage an e-commerce portal development program. The program is separated into individual projects that represent each area of development.
You have the following requirements:
✑ All work and progress on individual projects must be reflected in the e-commerce portal development program.
Each group must be able to manage their own tasks.
Exam 70-348: Question 4 - Image 1
You need to set up the e-commerce portal development program and its associated projects in Microsoft PPM.
Where should you add resources?
Correct Answer: C

Question 5 of 48
Your organization is using Microsoft PPM to manage large projects. Within the Microsoft PPM environment, you use SharePoint sites with task lists to manage smaller projects. You turn on the Timesheets feature.
You must collect information about the time that resources spend on all projects.
You need to ensure that you can capture timesheet data from the existing SharePoint task lists.
Which two actions will achieve the goal? Each correct answer presents a complete solution.
Correct Answer: A, C