Question 6 of 48
You are a project manager using Microsoft PPM.
You need to create a new project that uses one of your companys templates.
What are two ways to achieve the goal? Each correct answer presents a complete solution.
Correct Answer: A, B

Question 7 of 48
HOTSPOT -
You are evaluating the requirements for creating a new portfolio analysis.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
Hot Area:
Exam 70-348: Question 7 - Image 1
Correct Answer:
References:
https://technet.microsoft.com/en-us/library/dn641991.aspx Exam 70-348: Question 7 - Image 2
Question 8 of 48
Your organization is using Microsoft PPM to manage and track all projects.
The Project Management Office (PMO) needs to know which of the projects are aligned to the organizations strategic objectives.
You need to configure Microsoft PPM to use Portfolio Analysis.
Which two activities should you perform? Each correct answer presents part of the solution.
Correct Answer: B, D

Question 9 of 48
Your company has had several large projects fail due to cost overruns and the lack of available resources. These projects use an enterprise project type named
Large IT Project and use a workflow to govern the approval of the projects. The workflow consists of four phases: Initiate, Plan, Execute, and Close.
You need to use Microsoft PPM to compare the value that a new project provides with the cost of implementing the project.
Which three configuration changes should you make? Each correct answer presents part of the solution.
Correct Answer: A, B, E

Question 10 of 48
You are a portfolio manager for an organization that uses Microsoft PPM to manage projects. You plan to implement Power BI.
You need to import into Power BI by using the Microsoft Project Online content pack.
What should you do?
Correct Answer: B