SAFe Agilist Exam Questions

Here you have the best Scaled Agile SA practice exam questions.

Some things you may want to keep in mind about this practice exam questions:

  • You have 30 total questions to study from
  • Each page has 5 questions, making a total of 6 pages
  • You can navigate through the pages using the buttons at the bottom
  • This questions were last updated on September 16, 2024

Question 1 of 30


According to SAFe Principle #10, what should the Enterprise do when markets and customers demand change?

    Correct Answer: B

    According to SAFe Principle #10, the enterprise should reorganize the network around the new value flow when markets and customers demand change. This principle emphasizes the importance of adapting organizational structures to ensure that value delivery remains efficient and effective in the face of evolving market conditions. By reorganizing around the value flow, the enterprise can better align its resources and capabilities with the needs of the market, thus improving responsiveness and agility.

Question 2 of 30


Which statement is true about ART events?

    Correct Answer: B

    ART events, including PI Planning, the Scrum of Scrums, and the Inspect and Adapt workshop, are designed to create a closed-loop system ensuring continuous planning, execution, and feedback. Team events such as daily stand-ups, iteration planning, and iteration reviews occur within the context of these ART events, following a nested Plan-Do-Check-Adjust cycle.

Question 3 of 30


Which role serves as the servant leader for the Agile Release Train?

    Correct Answer: B

    The Release Train Engineer (RTE) serves as the servant leader for the Agile Release Train. The RTE facilitates Agile Release Train (ART) events and processes and supports teams in delivering value, embodying the principles of servant leadership to guide and steer the ART effectively.

Question 4 of 30


During the PI Planning event, when are planning adjustments agreed upon?

    Correct Answer: C

    Planning adjustments during the PI Planning event are agreed upon during the management review and problem-solving. This is the stage where management reviews the draft plans, identifies challenges like scope, resource constraints, and dependencies, and negotiates necessary changes to ensure a viable and feasible final plan.

Question 5 of 30


What is part of the role of the Scrum Master?

    Correct Answer: C

    The role of the Scrum Master includes facilitating all team events. This is a fundamental part of the Scrum Master's responsibilities, ensuring that all Scrum ceremonies are effectively organized and conducted. These events typically include Sprint Planning, Daily Standups, Sprint Reviews, and Sprint Retrospectives. Facilitating these events helps foster communication, collaboration, and continuous improvement within the team.