Question 6 of 1248

A project team has expressed concern that certain remote team members are not able to collaborate with the larger project team due to their work schedule. The project manager is confused since the entire team is located in the same time zone and believes there are other factors at play.

What should the project manager do next?

    Correct Answer: B

    Given the concern about remote team members not being able to collaborate despite being in the same time zone, it is crucial to understand the specific challenges they are facing. Examining the team's virtual needs will help identify any technological, communication, or other issues that may be hindering collaboration. This approach allows the project manager to gather necessary information and address the root cause effectively, ensuring that all team members can work together seamlessly.

Question 7 of 1248

A company is implementing a project with team members located in different countries and time zones. Individual performance is satisfactory, but the team's performance as a whole is low, especially in terms of group activities.

What should the project manager do?

    Correct Answer: B

    The project manager should focus on facilitating communication and team building. Given that individual performance is satisfactory but the team's overall performance in group activities is lacking, the primary issue appears to be related to coordination and teamwork. Since the team members are located in different countries and time zones, improving communication channels and fostering a sense of team cohesion can help bridge the gap and enhance collaborative efforts. This can be achieved through regular virtual meetings, team-building exercises, and the use of effective communication tools.

Question 8 of 1248

During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.

What should the project manager do next?

    Correct Answer: B

    In this scenario, the best course of action is to ask the product owner to prioritize the backlog with the project team. This ensures that any new mandatory features are properly assessed for their importance and urgency, and are incorporated into the project in a way that aligns with the team's capacity and the project's overall goals. Engaging the team in this process helps in setting realistic expectations, manages their workload effectively, and addresses the root cause of the frustration and failures from previous sprints.

Question 9 of 1248

Five agile teams working together on a product recently performed release planning. Midway through the project, each team showed that their progress was on track. When all of the teams integrated at the product level, many integration issues were observed. The overall product release progress declined with predictions showing the committed content will not be able to be accomplished.

What should the project manager have done differently?

    Correct Answer: D

    The project manager should have ensured frequent and continuous integration of work to obtain early feedback and continuous learning. By doing so, integration issues would be identified and addressed early in the development process, preventing the accumulation of problems that are only discovered at the product level.

Question 10 of 1248

A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.

What should the project manager do?

    Correct Answer: D

    The project is at risk of being delayed because a team member does not understand a new system. In this situation, the project manager should assign an experienced resource to support the team member. This approach ensures that the team member receives the necessary guidance and assistance promptly, helping to mitigate the risk of delay and ensuring the project stays on track. By leveraging the expertise within the team, the project can continue progressing while the team member gains the required knowledge.