PMI Agile Certified Practitioner

Here you have the best PMI PMI-ACP practice exam questions

  • You have 321 total questions to study from
  • Each page has 5 questions, making a total of 65 pages
  • You can navigate through the pages using the buttons at the bottom
  • This questions were last updated on October 12, 2024

Efficient Study Guide

We make emphasis on efficient preparation, and this study guide is the outcome of insane research and continuous improvement. Whether it's your first certification or just another one for your collection, this guide is here to help you pass the PMI Agile Certified Practitioner exam with top scores. Passing a certification exam has never been easy, but the important thing is to move in the right direction, and with this guide we can assure you that you will. Our content is updated with the latest exam changes and is used by thousands of professionals who successfully achieve their goals. Plus, you'll be part of a community ready to support you every step of the way. If you have questions, feel free to leave a comment and join the conversation - you're very close to achieving your goal and we're here to help!

PMI PMI-ACP Real Questions from Exam

The PMI Agile Certified Practitioner exam, also known as PMI PMI-ACP, is one of the most popular certifications of the year. Earning it has helped many professionals earn a higher salary and climb the career ladder. However, preparing properly is not an easy task. It requires not only time and effort, but also a considerable financial investment, just to have the opportunity to take it. If failing it is not in your plans, welcome, you are in the right place. At Examice we will give you the best set of real questions so you can pass your exam on the first try, optimizing your time and money to the maximum and focusing on the topics that really matter. Of course, we will need your dedication to make it happen, but we know that's not in doubt.

We cover exam goals

Each exam is different: some cover more topics, others less. The objectives of the exam define what knowledge you need to master and why it is important. It is essential to know these objectives before attempting to take the exam. You can find them on the provider's official site, where they will clearly indicate which topics to study. Of course, at Examice we take each of these objectives into account when designing our questions, in order to offer you a study experience as close as possible to the real exam.

PMI Agile Certified Practitioner Dumps Updated

Why would anyone want to study with questions that do not come from real exams? These questions often deal with different topics or have a different difficulty than the official exam, which ultimately ends up hindering more than it actually helps in preparing for the exam. If you study with real exam questions, you will have a better view of the topics being tested, the importance and frequency with which certain topics appear, and also the key words you should pay attention to in order to avoid falling into trap questions. This allows you to be prepared in a much more effective way than any other resource could offer. In addition, you will have the support of a community of people who will guide you every step of the way.

Why choose us?

I know what you are thinking, why should I trust us to prepare me for something so valuable and difficult, that requires so much time and money? The answer is simple: this is the best way to prepare for PMI Agile Certified Practitioner. No course or mock exam will offer you such a complete knowledge. Why? Because none recreates 100% of the real exam questions as we do here. To pass, it's not enough to know the theoretical content, you also need to learn how to answer the questions, identify misleading words and understand how the testers think. Only then will you know that your answers are correct.

Why not use the ExamTopics alternative?

ExamTopics is a well-known site in this field; however, its reputation has declined considerably due to repeated lies to its users. They claim that their service is free when in fact it comes at a high cost, and furthermore, most of the answers they provide are incorrect. You don't have to take our word for it, you can check out their TrustPilot reviews. We, however, are committed to providing accurate answers with detailed explanations to help you truly understand the concepts, all at less than a quarter of their price.

Pass PMI Agile Certified Practitioner Guaranteed

We understand that we haven't convinced you yet and you're right, we are not salespeople; we are simply passionate about the world of technology. That's why we don't want you to leave without living the experience with us. We decided to offer you the opportunity to study on our platform without any risk. If you don't pass your exam, we will give you all your money back, every penny! We are so confident in the quality of our exams that wewe will give you all your money back, every penny! We are so confident in the quality of our exams that we offer this guarantee because we believe in the success of our users. So, why not give it a try? You have nothing to lose and everything to gain. Join us now and get the best PMI PMI-ACP exam preparation available.

Question 1 of 321

A newly formed development team experienced difficulty with accurately estimating product backlog items. As a result, the team failed to deliver all of the features in the sprint backlog for the past two iterations.

What should the team do to improve the accuracy of their estimates?

    Correct Answer: D

    To improve accuracy in estimating product backlog items, the team should begin tracking estimated effort metrics as an input to performance evaluation. Tracking these metrics over several sprints can help the team understand their velocity and make more accurate estimates, addressing the root cause of their current difficulties. Sprint duration should remain fixed to have a consistent basis for measurement, and increasing team size or discussing estimating techniques during daily scrums are not appropriate solutions.

Question 2 of 321

Midway through a sprint, the scrum master identifies that reassigning a certain task could help the team meet its sprint's goals.

What should the scrum master do next?

    Correct Answer: D

    In Scrum, the development team is self-organizing and self-managing. The Scrum Master facilitates the process but does not directly assign or reassign tasks. Therefore, the Scrum Master should allow the team to decide if the task should be reassigned to ensure they meet their sprint goals.

Question 3 of 321

During the iteration planning of a newly on boarded agile team, the product owner adds a set of high priority user stories into the iteration backlog.

What should the team do first to define the tasks need to implement the user stories?

    Correct Answer: A

    In an agile team, the principle of self-organization is crucial. Teams are encouraged to independently manage their tasks and workflows. After high-priority user stories are added to the iteration backlog, it is essential for the team to self-organize to define the necessary tasks for implementation. This approach allows the team to leverage collective knowledge, skills, and intercommunication to efficiently break down user stories into actionable tasks and ensure that all aspects of the implementation are considered.

Question 4 of 321

A project's first iteration contains item A, and its second iteration contains item B. The first iteration is behind schedule, which will impact the second iteration.

Since items A and B are similar, a team member suggests beginning the design of item B.

What should the agile practitioner do?

    Correct Answer: A

    In agile practices, the focus should remain on completing the current iteration before starting tasks for the next iteration to avoid spreading the team's attention too thin. By deferring the design of item B until the second iteration is being planned, it ensures that any learnings or dependencies from item A are addressed adequately. This approach minimizes the risk of cascading issues related to the delay of item A and maintains a disciplined and manageable workflow.

Question 5 of 321

An Agile team is under pressure to deliver an application. The product owner anticipates many change requests from customers once the product is released.

What should the agile team do?

    Correct Answer: B

    The Agile team should continuously work with the product owner to do backlog refinement and product reviews. This approach aligns with the Agile principle of embracing change and adapting to new information. Continuously refining the backlog ensures that the team's efforts are always focused on the most valuable and current requirements, while regular product reviews help validate the product's progress and make necessary adjustments based on feedback. This method maintains flexibility and responsiveness to customer needs, which is essential in an Agile environment.