Architecting Advanced HPE Server Solutions

Here you have the best HP HPE0-S22 practice exam questions

  • You have 39 total questions to study from
  • Each page has 5 questions, making a total of 8 pages
  • You can navigate through the pages using the buttons at the bottom
  • This questions were last updated on November 15, 2024
Question 1 of 39

A customer has a Hadoop big data and analytics solution. The customer needs a server upgrade to improve performance for this solution and plans to add more solutions that draw on the data, such as a Cassandra NoSQL database. The customer is interested in a flexible HPE Big Data Reference Architecture approach.

Which solution meets the customers needs?

    Correct Answer: B

    The HPE Apollo 4530 System is designed for big data and analytics solutions, providing co-located compute and storage nodes, which are essential for high-performance requirements. This system can also support extensions for other data solutions like Cassandra NoSQL databases. Given these capabilities, the HPE Apollo 4530 Systems effectively meet the customer's need for a flexible HPE Big Data Reference Architecture approach, ensuring both performance improvement and scalability.

Question 2 of 39

A customer recently purchased an HPE Moonshot chassis to host its internal website. Subsequently, the customer reports difficulties deploying new cartridges in an efficient manner. The customer suggests exchanging the solution for a more traditional server platform.

What can the architect demonstrate to the customer to help solve the problem while preserving the validity of the original design solution?

    Correct Answer: D

    Using iLO (Integrated Lights-Out) remote console provides a comprehensive solution designed for HPE servers, including the Moonshot chassis. iLO allows administrators to perform graphical installations and manage nodes remotely with a user-friendly interface. It enables efficient deployment and management of new nodes without the need for additional hardware modules, preserving the original design solution while addressing the customer's difficulties.

Question 3 of 39

A customer is planning a multi-threaded HPC solution that would benefit from threads running in parallel.

The architect selects the HPE Apollo 6000 and needs to choose between the HPE XL230a and the XL250a compute tray.

What is one reason for choosing the XL250a tray?

    Correct Answer: B

    The HPE XL250a server supports dual accelerators. This feature can significantly boost the performance of multi-threaded HPC applications by allowing the use of powerful accelerators such as NVIDIA Tesla or Intel Xeon Phi. By supporting dual accelerators, the XL250a tray can offer higher computational power compared to the XL230a tray, making it a more suitable choice for customers requiring enhanced performance capabilities for parallel processing tasks.

Question 4 of 39

An architect takes the following notes during a meeting with a customer:

✑ plans to introduce an entirely new service offering to customers

✑ servers will be virtualized and will consume large amounts of storage space

✑ project is to operate in an isolated section of the data center with limited access to the corporate network

✑ need flexibility to grow quickly as required by the new service demands on the infrastructure

✑ has no repeatable process for firmware management

✑ concerned about how long it will take for the project team to become productive on the new infrastructure

Which solution should the architect propose to help the customer overcome all of its project challenges?

    Correct Answer: C

    The HPE ConvergedSystem 700 solution with HPE 3PAR storage is most suitable because it addresses several key project challenges: the need for quick team productivity, flexibility for growth, and isolated operations with large storage consumption. The ConvergedSystem 700 is designed to provide faster deployment and easier management, which will help the team become productive more quickly and efficiently handle firmware management processes.

Question 5 of 39

View the Exhibit.

Refer to the exhibit. A customer has an HPE c7000 enclosure managed by HPE OneView with HP BL460c Gen9 servers in a vSphere cluster. The customer has multiple vLANs trunked from the top of rack (TOR) switches to the Virtual Connect modules in the enclosure. Due to network Access Control List (ACL) requirement and guidelines from the networking department, all network traffic should be forced to an upstream switch using the Virtual Connect "Private Network" feature.

The customer reports slow network response.

Which modification can the architect recommend to improve network performance?

    Correct Answer: D

    To improve network performance, it is recommended to put the vMotion network in a separate uplink set and disable the 'Private Network' feature. The 'Private Network' feature forces all traffic to upstream switches, which can cause congestion and slow network response, especially for traffic-heavy operations like vMotion. By isolating the vMotion network, you can reduce the amount of traffic on the other networks and improve overall performance.