Exam 3V0-42.20 All QuestionsBrowse all questions from this exam
Question 27

According to the Discover Task of the Engagement Lifecycle, which statement would be classified as a risk? (Choose the best answer.)

    Correct Answer: C

    A merger and acquisition process that was recently completed with the new company on-boarding not yet completed represents a risk. This situation involves potential uncertainties and challenges such as integration issues, alignment of systems and processes, and cultural differences, which can impede the progress of the project. These uncertainties inherently introduce risk to the stability and continuity of ongoing and planned operations.

Discussion
vKramerOption: C

B is a requirement, D is a constraint. C is a risk since the new company may introduce new thinks which cannot be "Discovered" now.

VMwareARCHIOption: C

C is the correct. D is a constraint

Me_Loi1Option: C

C is correct

diegof1Option: C

C is correct because is a risk.

MJ86Option: D

Option B is wrong. The correct answer should be D. Reason: Option D talks about using the existing servers. Now if the servers are too old, then it may not be supported by NSX-T

diegof1

The D option talks about reuse existing hardware. It doesn’t talk about if it is new or old.

TachinskyOption: C

A = assumption B = Requirement C = Risk D = Constraint

outlawwwOption: C

I don't understand how B can be considered a risk for NSX-T design. If anything is a non-functional constraint, since the design must incorporate all the requirements to meet the PCI-DSS standard.

AT45816Option: C

C is the correct.

borracho13Option: D

C is a constraint. D is a risk because you don't know if the existing hardware is compatible or under warranty, or in workign condition.

borracho13

I'm going back on this. D is a constraint, whereas C has the biggest negative impact to the project.

ertin74Option: B

On a business perspective, B is the real risk

AlchotOption: C

B should be correct. NSX is implemented to meet requirements and certify standards or government information security requirements. This is a high risk that can affect the business. C is also a risk that can affect the project promotion and budget or even critical stakeholders stability.

airmouse1234Option: C

C is correct

DCL202Option: B

D is a constraint. Both B and C are risks, but B is a pass/fail that could have a big impact. Answer is B

nick2u

I would go with C...This is design NSX, it would be irrelavent if the business got cert for financial service. One way or anther if wont affect uitlizing NSX.

BrianOCOption: B

In the RRCA conceptual phase, the biggest risks are those that have a high chance, high impact, or a combination of both. You can mitigate those risks, but they must still be called out. Technically every assumption in a design is a risk. (D) could be an assumption, but it’s after the discovery phase so it could be an actual assessment. (C) is a constraint on the surface, though when combined with other things could then also become a risk (B) is a risk but is lacking major impact. Answer is "B"

Pal68

On reflection, as the business need to etain certification to provide financial services to end customers, B is the bigger impact risk than C, so B is the best answer..

FornaxOption: A

I'm gonna be crazy and say that A is the right answer. A risk of a NSX-T design doesn't care about PCI, and doesn't care about a merger. However, if you could potentially lose power and cooling for your racks, that is a risk!

Fornax

Nevermind. I take back my crazy answer.