3V0-42.20 Exam QuestionsBrowse all questions from this exam

3V0-42.20 Exam - Question 27


According to the Discover Task of the Engagement Lifecycle, which statement would be classified as a risk? (Choose the best answer.)

Show Answer
Correct Answer: C

A merger and acquisition process that was recently completed with the new company on-boarding not yet completed represents a risk. This situation involves potential uncertainties and challenges such as integration issues, alignment of systems and processes, and cultural differences, which can impede the progress of the project. These uncertainties inherently introduce risk to the stability and continuity of ongoing and planned operations.

Discussion

15 comments
Sign in to comment
vKramerOption: C
Feb 14, 2021

B is a requirement, D is a constraint. C is a risk since the new company may introduce new thinks which cannot be "Discovered" now.

VMwareARCHIOption: C
Feb 20, 2021

C is the correct. D is a constraint

MJ86Option: D
Feb 12, 2021

Option B is wrong. The correct answer should be D. Reason: Option D talks about using the existing servers. Now if the servers are too old, then it may not be supported by NSX-T

diegof1
Apr 9, 2021

The D option talks about reuse existing hardware. It doesn’t talk about if it is new or old.

diegof1Option: C
Apr 6, 2021

C is correct because is a risk.

Me_Loi1Option: C
Apr 22, 2021

C is correct

outlawwwOption: C
Mar 9, 2023

I don't understand how B can be considered a risk for NSX-T design. If anything is a non-functional constraint, since the design must incorporate all the requirements to meet the PCI-DSS standard.

TachinskyOption: C
Aug 10, 2023

A = assumption B = Requirement C = Risk D = Constraint

FornaxOption: A
May 30, 2021

I'm gonna be crazy and say that A is the right answer. A risk of a NSX-T design doesn't care about PCI, and doesn't care about a merger. However, if you could potentially lose power and cooling for your racks, that is a risk!

Fornax
May 30, 2021

Nevermind. I take back my crazy answer.

BrianOCOption: B
Aug 2, 2021

In the RRCA conceptual phase, the biggest risks are those that have a high chance, high impact, or a combination of both. You can mitigate those risks, but they must still be called out. Technically every assumption in a design is a risk. (D) could be an assumption, but it’s after the discovery phase so it could be an actual assessment. (C) is a constraint on the surface, though when combined with other things could then also become a risk (B) is a risk but is lacking major impact. Answer is "B"

Pal68
Oct 5, 2021

On reflection, as the business need to etain certification to provide financial services to end customers, B is the bigger impact risk than C, so B is the best answer..

DCL202Option: B
Oct 13, 2021

D is a constraint. Both B and C are risks, but B is a pass/fail that could have a big impact. Answer is B

nick2u
Nov 20, 2021

I would go with C...This is design NSX, it would be irrelavent if the business got cert for financial service. One way or anther if wont affect uitlizing NSX.

airmouse1234Option: C
Apr 7, 2022

C is correct

AlchotOption: C
Sep 24, 2022

B should be correct. NSX is implemented to meet requirements and certify standards or government information security requirements. This is a high risk that can affect the business. C is also a risk that can affect the project promotion and budget or even critical stakeholders stability.

ertin74Option: B
Nov 4, 2022

On a business perspective, B is the real risk

borracho13Option: D
Jul 7, 2023

C is a constraint. D is a risk because you don't know if the existing hardware is compatible or under warranty, or in workign condition.

borracho13
Jul 7, 2023

I'm going back on this. D is a constraint, whereas C has the biggest negative impact to the project.

AT45816Option: C
Feb 2, 2024

C is the correct.