An administrator is using vRealize Operations for capacity modeling to determine how many more ESXi servers are needed to increase time remaining and capacity remaining score.
What can be used to accomplish this goal?
An administrator is using vRealize Operations for capacity modeling to determine how many more ESXi servers are needed to increase time remaining and capacity remaining score.
What can be used to accomplish this goal?
To determine how many more ESXi servers are needed to increase time remaining and capacity remaining score, an administrator can use the What-If Analysis in vRealize Operations. This feature allows administrators to model different scenarios and assess the impact of adding or removing resources in the cluster, helping them make informed decisions on capacity planning.
For me it A What-If Analysis : https://docs.vmware.com/en/vRealize-Operations/8.10/com.vmware.vcom.core.doc/GUID-2D2A0CA2-FA40-4D15-AC1B-C2435A63E33A.html