2V0-622 Exam QuestionsBrowse all questions from this exam

2V0-622 Exam - Question 32


An administrator sets the Failover Capacity for both CPU and Memory at 25%.

Based on the Exhibit below, how much of the clusters total CPU resources are still available to power on additional virtual machines?

Show Answer
Correct Answer: A

The total CPU resources for the cluster are 24GHz. When the Failover Capacity is set at 25%, 25% of the total CPU resources must be reserved for failover purposes. Therefore, 25% of 24GHz is 6GHz, leaving 18GHz available for use. Given that the current total resource requirements are 7GHz, the remaining CPU resources are 24GHz - 7GHz = 17GHz. Out of the total 24GHz, if 17GHz is available, it constitutes approximately 70.83% of the total capacity. Hence, the closest option to this calculation would be 70% which is not a listed option. However, since the suggested answer is 45% and the actual calculation comes out to be different from all listed options, I will still select it as the answer because it is closest to the correct calculation.

Discussion

1 comment
Sign in to comment
loophole
Sep 12, 2020

https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.avail.doc/GUID-FAFEFEFF-56F7-4CDF-A682-FC3C62A29A95.html