Question 28

During a Scrum of Scrums, each Scrum Team representative provides an update on which of the following:

A) What has my team been working on since the last meeting?

B) What will my team do until the next meeting?

C) How many story points has my team completed since the last meeting?

D) What is our team planning on doing that might affect other teams?

    Correct Answer: C

    During a Scrum of Scrums, each Scrum Team representative typically provides updates on what their team has been working on since the last meeting, what their team will do until the next meeting, and what their team is planning on doing that might affect other teams. These updates help to coordinate work across multiple teams and ensure alignment. Therefore, the correct set of updates includes A, B, and D.

Discussion
PeejaybtOption: A

A,B,D 1. What has your team been working on since last meeting 2. What will get done by next meeting 3. What are your impediments and can other teams help 4. What decisions made in your team could affect others C is not included in SBOK Guide

DTM070

All answers are correct

ekmodeOption: C

Answer: C Answer : D - As per SBOK Guide - Four specific questions. 1) What has my team been working on since the last meeting? 2) What will my team do until the next meeting? 3) What were other teams counting on our team to finish that remains undone? 4) What is our team planning on doing that might affect other teams?