Scrum Master Certified Exam - Question 45


Which of the following best defines the team velocity metric used to measure team performance?

Show Answer
Correct Answer: B

Team velocity is the total number of story points completed in a given Sprint. This metric is used to gauge how much work the team can handle in future sprints based on their past performance.

Discussion

1 comment
Sign in to comment
Jozef_joeOption: B
Aug 12, 2023

B, SBOK 11.2.2.4 Metrics and Measuring Techniques - Team velocity—Number of story points done in a given Sprint