Between traditional Project Management and Scrum, differences exist in how quality is achieved and/or implemented. In this respect, which of the following is NOT true?
Between traditional Project Management and Scrum, differences exist in how quality is achieved and/or implemented. In this respect, which of the following is NOT true?
In Scrum, it is primarily the Product Owner who defines the Acceptance Criteria for the User Stories, though the Scrum Team may collaborate and ask clarifying questions to ensure mutual understanding. The Scrum Master facilitates the process but does not directly define the Acceptance Criteria.
The answer is C