Exam Scrum Master Certified All QuestionsBrowse all questions from this exam
Question 14

While assisting the Product Owner in developing a Prioritized Product Backlog, the Scrum Master must consider the primary factors on which the Prioritized

Product Backlog is based-on. Which of the following are those primary factors?

A) Value -

B) Dependencies -

C) Risk -

D) Deliverables -

    Correct Answer: A

    The Prioritized Product Backlog is primarily based on three factors: value, risk or uncertainty, and dependencies. These factors help ensure that the most critical and impactful items are prioritized to maximize business value and manage potential risks and dependencies effectively. Deliverables are not considered a primary factor in prioritizing the Product Backlog.

Discussion
patricpotter1992

I think the answer that fit better is A,B and C.

e72ac02Option: A

8.5.3.1 The Prioritized Product Backlog is based primarily on three factors—value, risk or uncertainty, and dependencies

Subarashi

A, B and C!