Exam Scrum Master Certified All QuestionsBrowse all questions from this exam
Question 39

Listed below are some risks and issues that might be encountered during the course of a project. Identify which of the following are risks (not issues).

A) After extensive training, marketing representatives might still not be ready to take orders after the project is launched.

B) The painting crew might be delayed due to heavy rain, which could negatively impact the project schedule.

C) Funding was not approved.

D) Requirements, as currently defined, are unclear.

    Correct Answer: D

    Risks are potential events that may occur in the future and could have a negative impact on the project, while issues are problems that are currently happening. Option A describes a potential future event where marketing representatives might not be ready after training, which is a risk. Option B describes the possibility of heavy rain causing a delay, which is also a risk. Option C indicates that funding was not approved, meaning it's an existing problem, making it an issue. Option D states that the requirements are unclear, which is a present problem, making it an issue. Therefore, options A and B are both risks.

Discussion
ekmodeOption: D

Answer: D , SBOK GUIDE -7.3.1-Difference between Risks and Issues- REF EXAMPLE

bovosOption: D

A and B=risks C and D=Issues