Question 32

Which of the following statements about Release Planning Session is/are Correct?

A) Release Planning Sessions are conducted to develop a plan that defines when various sets of usable functionality or products will be delivered to the customer.

B) Release Planning Sessions enable the Scrum Team to have an overview of the releases and delivery schedule for the product they are developing.

C) Whether the releases will follow a phased deployment pattern or a continuous deployment pattern depends on the stakeholder requirements.

D) Release Planning Sessions should produce a detailed Release Plan for the entire project.

    Correct Answer: B

    Release Planning Sessions serve multiple purposes, including defining when various sets of usable functionality or products will be delivered to the customer and providing the Scrum Team with an overview of the release and delivery schedule. This helps the team align expectations with the Product Owner and relevant stakeholders. Therefore, combining both statements A and B covers these essential aspects of release planning. On the other hand, C and D introduce specifics about deployment patterns and the level of detail in the Release Plan that are not universally required elements of Release Planning Sessions.

Discussion
EmyyaOption: B

Correct answer is A and B