Question 48

Suppose you are a Scrum Master on a project to design a metro rail system for a city. It has been brought to your attention that the Product Owner wants to change the Acceptance Criteria for one of the User Stories committed to for the current Sprint because the customer has changed a critical business requirement.

Which one of the following statements presents the best solution for such a situation?

    Correct Answer: B

    When a change in requirements arises during an ongoing Sprint, the best practice is for the Product Owner to add the new requirement to the Product Backlog. This approach maintains the focus and commitment of the Scrum team to the current Sprint's goals while ensuring that the new requirements are prioritized for future Sprints. Changes should not disrupt the current Sprint unless they are exceptionally critical and cannot wait, in which case the Sprint may need to be canceled. However, the general protocol is to handle new requirements in future Sprints to avoid constant disruption and to ensure a stable development process.

Discussion
koninaOption: D

D "Whenever there is a problem or new requirement that needs to be addressed immediately and mandates a change affecting the current Sprint, the Product Owner terminates the Sprint, with approval from relevant stakeholders. Once terminated, the Sprint will be re-planned and restarted to incorporate the new requirements."

pepe_uchihaOption: C

Respuesta: C "Si hay una solicitud de cambio que puede tener un impacto significativo en un Sprint en curso, el propietario del producto, luego de consultar con las partes interesadas relevantes, decide si el cambio puede esperar hasta el próximo Sprint o si representa una situación urgente que puede requerir finalizar el Sprint actual y comenzando uno nuevo."