Scrum Master Certified Exam - Question 50


You are a Scrum Master on a project creating an optical fiber cable network across the country. The project has reached the Create User Stories process. Which of the following is NOT an input to this process?

Show Answer
Correct Answer: B

The key inputs for the Create User Stories process in Scrum are the Scrum Core Team, the Prioritized Product Backlog, Personas, and the Done Criteria. Identified Risks are not considered a direct input to this process as they do not specifically contribute to the creation of User Stories. Therefore, the correct answer is Identified Risks.

Discussion

2 comments
Sign in to comment
ChubaOption: D
Dec 8, 2023

Done Criteria

e72ac02Option: B
Mar 10, 2024

b is the correct answer