Question 35

One of the responsibilities of the Scrum Master is to facilitate timely identification of all risks faced by the Scrum Team. As the Scrum Master for a team working on a banking application project, which of the following techniques would you suggest for comprehensive risk identification?

    Correct Answer: D

    A risk meeting is a comprehensive method for identifying risks as it allows the entire team to discuss and identify potential threats collaboratively. This approach ensures that diverse perspectives are considered, leading to a more thorough identification of risks. Techniques like Risk Appetite or Probability Impact Grid are more about assessing and prioritizing risks rather than identifying them in a collaborative manner.

Discussion
Mi_WindsorOption: B

The answer is B