Scrum Master Certified Exam QuestionsBrowse all questions from this exam

Scrum Master Certified Exam - Question 26


Which of the following is true about a Prioritized Product Backlog?

Show Answer
Correct Answer: B

A Prioritized Product Backlog should have items that provide greater value or are more critical at the top, even if they are riskier. The rationale is that addressing such high-value items early on can potentially bring significant progress and also help in identifying and mitigating risks early in the project. A Risk-adjusted Prioritized Product Backlog factors in value and risk, ensuring high-risk items are given appropriate attention in the development process.

Discussion

2 comments
Sign in to comment
PeejaybtOption: B
Oct 24, 2022

B is correct

Mi_WindsorOption: B
Jul 10, 2023

B is the correct answer