Scrum Master Certified Exam - Question 15


You are the Scrum Master for a team that is working on a project for a chemical engineering company. During one of the Sprints, the Product Owner suggests changes to the Acceptance Criteria on the basis of new requirements by the stakeholders. Which of the following best describes the steps that should be taken next in this situation?

Show Answer
Correct Answer: C

In Scrum, changes to acceptance criteria that occur during a sprint are often handled by adding the updated requirements to the Product Backlog. The Scrum Team should not abandon their sprint goal to re-work the deliverable immediately but acknowledge the change and address it in a future sprint. Therefore, the best course of action is for the deliverable to be rejected based on the new requirements and added to the Prioritized Product Backlog with updated acceptance criteria, to be worked on in a subsequent sprint.

Discussion

2 comments
Sign in to comment
ksk2484Option: C
Mar 10, 2022

C is the Correct Answer

Mi_WindsorOption: C
Jul 10, 2023

C is the correct answer