Scrum Master Certified Exam - Question 1


All of the following statements about Risk Communications are true, EXCEPT:

Show Answer
Correct Answer: B

While it is essential for stakeholders to be continuously informed about risks, and for the Product Owner to prioritize and communicate these risks, daily standup meetings do not typically include the Product Owner. Instead, the Scrum Team discusses specific risks and challenges related to their tasks with the Scrum Master during these meetings. Thus, the statement about discussing risks with the Product Owner during Daily Standup Meetings is incorrect.

Discussion

3 comments
Sign in to comment
patricpotter1992Option: B
Jul 29, 2021

Correct answer B.

StephanJoOption: B
Apr 21, 2022

B The Scrum Team may also discuss specific risks related to their Tasks with the Scrum Master during Daily Standup Meetings.

Mi_WindsorOption: B
Jul 10, 2023

Correct answer is B