Question 55

Which of the following meetings is not usually Time-boxed?

    Correct Answer: B

    Scrum of Scrums meetings are not usually time-boxed to allow for more comprehensive information sharing between teams. This type of meeting focuses on coordination and integration across multiple scrum teams, which may require flexibility in timing depending on the complexity of the projects involved.

Discussion
Jozef_joeOption: B

B, page 278 of SBOOK 13.2.2.1 Scrum of Scrums Meeting - They are usually not Time-boxed to allow for more sharing of information between teams.