While creating the Sprint Backlog, the Scrum Team along with the Scrum Master and Product Owner must consider which of the following as inputs?
While creating the Sprint Backlog, the Scrum Team along with the Scrum Master and Product Owner must consider which of the following as inputs?
When creating the Sprint Backlog, it is important to consider the length of the sprint, the previous sprint velocity, dependencies, and the team calendar. The length of the sprint determines the time frame within which the team will work, the previous sprint velocity helps in forecasting how much work can be taken up, dependencies highlight any work that needs to be completed in a sequence, and the team calendar ensures availability and identifies potential conflicts.
C is the correct answer