Scrum Master Certified Exam QuestionsBrowse all questions from this exam

Scrum Master Certified Exam - Question 6


At the end of each Sprint the Scrumboard is _________.

Show Answer
Correct Answer: CD

At the end of each Sprint, the Scrumboard is reset or wiped off, which is standard practice in Scrum. This allows the team to start fresh with the new tasks and updates for the next Sprint, ensuring clarity and focus on the current Sprint's work.

Discussion

3 comments
Sign in to comment
ekmodeOption: D
Dec 25, 2020

Answer: D , SBOK GUIDE - 10.1.3.2 - Reset or wiped off

patricpotter1992Option: D
Jul 29, 2021

Answer: D.

lusalas16Option: D
Jan 29, 2023

SBOK GUIDE - 10.1.3.2 - Reset or wiped off