Scrum Master Certified Exam QuestionsBrowse all questions from this exam

Scrum Master Certified Exam - Question 30


During a Scrum of Scrums Meeting certain questions are answered. Which of the following are the questions answered?

A) What has my team been working on since the last meeting?

B) What will my team do until the next meeting?

C) What were other teams counting on our team to finish that remains undone?

D) What is our team planning on doing that might affect other teams?

Show Answer
Correct Answer: C,D

C

Reference:

http://www.cs.vsu.ru/~svv/spm/SBOK_Guide_3rd_edition_English_Sample.pdf

(59)

Discussion

5 comments
Sign in to comment
ekmodeOption: D
Dec 12, 2020

Answer : D - As per SBOK Guide - Four specific questions. 1) What has my team been working on since the last meeting? 2) What will my team do until the next meeting? 3) What were other teams counting on our team to finish that remains undone? 4) What is our team planning on doing that might affect other teams?

rthakkarOption: D
Jan 11, 2023

As per SBOK Guide - Four specific questions. 1) What has my team been working on since the last meeting? 2) What will my team do until the next meeting? 3) What were other teams counting on our team to finish that remains undone? 4) What is our team planning on doing that might affect other teams?

SubarashiOption: D
Jun 7, 2023

Answer: D. SBOK Guide 13.3.5

CharloPcOption: D
Jun 14, 2023

Some of the answers like this answer for this question is not correct. The answer is D which is expressly stated in SBOG 4th Edition page 292

Mi_WindsorOption: D
Jul 10, 2023

The correct answer id D