Question 30

During a Scrum of Scrums Meeting certain questions are answered. Which of the following are the questions answered?

A) What has my team been working on since the last meeting?

B) What will my team do until the next meeting?

C) What were other teams counting on our team to finish that remains undone?

D) What is our team planning on doing that might affect other teams?

    Correct Answer: D

    C

    Reference:

    http://www.cs.vsu.ru/~svv/spm/SBOK_Guide_3rd_edition_English_Sample.pdf

    (59)

Discussion
ekmodeOption: D

Answer : D - As per SBOK Guide - Four specific questions. 1) What has my team been working on since the last meeting? 2) What will my team do until the next meeting? 3) What were other teams counting on our team to finish that remains undone? 4) What is our team planning on doing that might affect other teams?

rthakkarOption: D

As per SBOK Guide - Four specific questions. 1) What has my team been working on since the last meeting? 2) What will my team do until the next meeting? 3) What were other teams counting on our team to finish that remains undone? 4) What is our team planning on doing that might affect other teams?

Mi_WindsorOption: D

The correct answer id D

CharloPcOption: D

Some of the answers like this answer for this question is not correct. The answer is D which is expressly stated in SBOG 4th Edition page 292

SubarashiOption: D

Answer: D. SBOK Guide 13.3.5