A Scrum Team wants to conduct a meeting in which they plan to deliberate on ways to improve team collaboration and effectiveness in future. This can be identified as which type of meeting?
A Scrum Team wants to conduct a meeting in which they plan to deliberate on ways to improve team collaboration and effectiveness in future. This can be identified as which type of meeting?
The meeting intended to deliberate on ways to improve team collaboration and effectiveness in future is called a Retrospect Project meeting. This type of meeting focuses specifically on reviewing what worked well, what didn’t, and identifying actionable improvements for future projects or sprints.
Answer: C
answer: C
C, SBOK page 258 - 112.2.2.1 Retrospect Project Meeting - The Retrospect Project Meeting is a meeting to determine ways in which team collaboration and effectiveness can be improved in future projects.