Scrum Master Certified Exam - Question 47


A Scrum Team wants to conduct a meeting in which they plan to deliberate on ways to improve team collaboration and effectiveness in future. This can be identified as which type of meeting?

Show Answer
Correct Answer: A,C

The meeting intended to deliberate on ways to improve team collaboration and effectiveness in future is called a Retrospect Project meeting. This type of meeting focuses specifically on reviewing what worked well, what didn’t, and identifying actionable improvements for future projects or sprints.

Discussion

3 comments
Sign in to comment
skrzekOption: C
Aug 6, 2021

Answer: C

bovosOption: C
Nov 26, 2021

answer: C

Jozef_joeOption: C
Aug 12, 2023

C, SBOK page 258 - 112.2.2.1 Retrospect Project Meeting - The Retrospect Project Meeting is a meeting to determine ways in which team collaboration and effectiveness can be improved in future projects.