Exam Scrum Master Certified All QuestionsBrowse all questions from this exam
Question 51

You are the Scrum Master of a project to construct an IT Tech Park. This project requires adhering to stringent quality standards at every stage of development. A

Scrum Core Team is formed for this project in which the Scrum Master is supposed to facilitate a "team first" mentality when it comes to quality. You must ensure all of the following to maintain quality in Scrum, EXCEPT:

    Correct Answer: A

    Fixing quality-related errors only at the end contradicts the principles of Scrum, which emphasize continuous integration, continuous testing, and regular feedback throughout the development process. Ensuring quality during all stages, rather than at the end, is critical to maintaining high standards and avoiding larger, compounded issues. Therefore, not fixing quality errors until the end does not align with Scrum practices.

Discussion
ChubaOption: A

Answer is A. Any quality related error must be fixed only at the end to ensure that the deliverable is Done.