Question 25

Scrum Masters have to solve both internal and external impediments for the Scrum team during the Create Deliverables process. To do so, they record the impediments in the Impediment Log during _________________________.

A) Daily Standup Meetings.

B) Sprint Review Meetings.

C) Release Planning Meetings.

D) Sprint Planning Meetings.

    Correct Answer: A

    Scrum Masters typically record the impediments in the Impediment Log during Daily Standup Meetings. These meetings are held each day of the sprint and are used to discuss progress, plans, and any obstacles faced by the team. Impediments are identified and recorded during these meetings so that they can be addressed promptly.

Discussion
ekmodeOption: A

Answer: A, SBOK GUIDE-10.1.1.14-Impediment Log* Impediments should be formally recorded by the Scrum Master in an Impediment Log, and can be discussed during Daily Standup Meetings and Sprint Review Meetings as appropriate.

DTM070Option: A

Answer is A & B