Question 20

You are the Scrum Master on a project to develop machine parts for automobile manufacturing. The Product Owner on your project proposes to use Utility

Function to find out the stakeholders' risk tolerance level. Which of the following is NOT a risk tolerance classification?

    Correct Answer: C

    In the context of risk tolerance classification, the common categories are Risk Averter, Risk Seeker, and Neutral Risk Taker. These classifications relate to how individuals or organizations approach risk. 'Risk Mitigator' is not a standard classification of risk tolerance; rather, it refers to actions taken to reduce or manage risk. Therefore, 'Risk Mitigator' is the correct answer as it does not fit with the standard categories of risk tolerance.

Discussion
e72ac02Option: C

c is the answer

weiweiOption: C

SBOK 7.3.2