Who among the following can directly approve changes recommended in the project?
Who among the following can directly approve changes recommended in the project?
In a Scrum framework, the Product Owner is responsible for the product backlog and ultimately has the authority to approve and prioritize changes recommended in the project. This includes making decisions about changes and ensuring they align with the product's goals and vision. The Product Owner has the closest understanding of the project's needs and stakeholder requirements, making them best suited to approve changes directly.
Answer: A - Product Owner
this is a trick question. as it didn't state small change it would be B. small changes are approved by the product owner. however it did not state small changes
Answer A