Which of the following best describes why Epics are decomposed into smaller User Stories during a Sprint?
Which of the following best describes why Epics are decomposed into smaller User Stories during a Sprint?
Epics are decomposed into smaller User Stories because they are too large to be completed within a single Sprint. By breaking down Epics into more manageable pieces, teams can ensure that the work can be completed within the short time frame of a Sprint, allowing for better progress tracking and more achievable goals.
C. Some User Stories may be too large to handle within a single Sprint. These large User Stories are often called Epics. [SBOK GUIDE 9.1.3.1 , page 189
Agreed with you. C
cont'd.....Once Epics come up in the Prioritized Product Backlog to be completed in an upcoming Sprint, they are further decomposed into smaller User Stories.
C is the correct answer